Redevelopment Of Gold Mine And Processing Plant

Client: Gold Mine

Location: Goldfields

Capabilities Used

  • Lead EPCM consultant
  • Project Management
  • Site Execution

Rapallo was engaged by our client as the lead EPCM contractor to carry out the feasibility study and execution works to re-establish the a Gold Mining Operations to the nameplate rating of 750,000tpa following a significant period of closure. Rapallo’s scope included approximately $35M of work. The project and Rapallo’s scope covered the entire site, including:

  • The Processing plant
  • Haul roads & Airstrip
  • Power supply & Communications
  • Mine dewatering & Water supply
  • Surface workshop & Camp facilities

Rapallo provided the overall Project Management; Initial inspection and assessment of existing equipment; Cost estimating; Specification, tendering of vendor equipment; Engineering design and drafting; Management of vendor packages; Supply of general construction labour; and management of subcontractor labour on site.

WHAT OUR

CLIENTS SAY

GET IN TOUCH

If you have a project you’d like to discuss, please call us on (08) 6279 0900 or complete and submit the form below.

  • This field is for validation purposes and should be left unchanged.